A written direction given by the owner or principal to accelerate or re-sequence the being performed by the contractor under the contract
A not-for-profit professional organization for engineers.
Drawings, records, documents, and other information that reflect the actual conditions of a project as it was constructed.
Documents, such as drawings and specifications that have been reviewed and approved for use in construction.
A comprehensive list of all assets associated with a project, including details such as location, condition, and maintenance history.
The approved version of a project schedule used as a reference for measuring project performance.
A document listing the quantities and cost of materials and labour for a construction project.
A comprehensive list of materials, components, and assemblies required to construct a project.
Funds used to acquire or upgrade physical assets.
A written certificate which states that the constructed facility has achieved all the requirements in the contract at the date of practical completion.
A formal document that modifies the original contract terms, scope, or price.
Any actual or potential legal demand, action, or proceedings
The process of testing and verifying that all systems and components of a project are designed, installed, and functioning as intended.
Any of a number of events that may give rise to the ability for the contractor to claim compensation from the principal or owner.
A project management technique used to determine the sequence of tasks that directly impact the project completion date.
Any trait of the work (goods and / or services) which does not comply with the specifications of the contract.
A period following the completion of a project during which the contractor is responsible for correcting any defects.
The time for which a part or product is designed to work as it is specified or assumed to be able to work.
Any difference or disagreement between parties that is either wholly or partly unresolved.
A document that lists all the drawings for a project, including their status and revision history.
The process of investigating and evaluating a project or investment to confirm all facts and assess potential risks.
The expected total cost of a project when it is complete.
A form of contracting arrangement where the contractor is responsible for all activities from design, procurement, and construction to commissioning and handover.
A form of contracting arrangement where the contractor provides management services for the design, procurement, and construction phases.
A project management methodology that measures project performance and progress in terms of scope, time, and cost.
A risk for which the contractor is not responsible for.
Additional work that is outside the original contract scope.
A document issued at the end of a project indicating that all contractual obligations have been met.
A design phase that focuses on technical requirements and rough investment costs.
An organisation that provides standard suit of contract templates for projects.
A trade term indicating that the seller delivers goods to a ship at a specified port and the buyer pays for shipping and insurance.
An event for which a party affected by the event cannot be held responsible.
A visual project management tool that outlines the project schedule, showing tasks, durations, and dependencies.
A contract type where the contractor is compensated for actual costs incurred plus a fixed fee, up to a maximum price.
A project built on undeveloped land, where no previous construction exists.
Practices aimed at ensuring the health and safety of employees and the environment.
Systems providing heating, cooling, and ventilation to buildings.
The formal transfer of a project or asset from the contractor to the client.
A point in the project where work cannot proceed until an inspection or approval is completed.
Drawings or documents issued to the construction team for use in building the project.
A shorthand for the ICC Official Rules for the Interpretation of Trade Terms – Incoterms 2010 published by the International Chamber of Commerce.
A document detailing the inspection and testing requirements for a project.
A formal request for suppliers to submit a bid to provide goods or services.
A process to identify hazards and develop safe procedures for each task in a project.
An initial meeting where project stakeholders discuss the project objectives, scope, and plan.
A measurable value that demonstrates how effectively a project is achieving key objectives.
A defect not reasonably capable of being discovered by the principal through normal use and maintenance of the work.
A document indicating the intention to enter into a formal agreement.
The time between the initiation and completion of a process.
A process of evaluating the total cost of ownership of a project or asset, including initial, operating, and disposal costs.
Materials or equipment with long procurement times that require early ordering.
A contract in which the contractor agrees to complete a project for a fixed price.
Components and systems related to mechanical and electrical engineering in a project.
A process for managing changes in a project to ensure they are evaluated, approved, and implemented safely.
A document that provides information on the properties of hazardous chemicals and how to handle them safely.
The process of assembling and preparing the necessary resources to start a project.
NDA (Non-Disclosure Agreement):
A legal contract protecting confidential information from being disclosed.
A formal document authorizing the contractor to begin work on a project.
A testing process that evaluates the properties of a material, component, or system without causing damage.
Activities required to operate and maintain a project or asset after it is completed.
A representative of the project owner who oversees the contractor's work and ensures it meets the contract requirements.
A detailed diagram showing the piping and related components of a process system.
A person responsible for coordinating project activities and ensuring they are completed on time.
A document specifying the design requirements for piping systems.
The written outline of a principal’s requirements for the work for which they have entered an agreement with a contractor
A report documenting the progress of a project
A document requesting materials needed for a project.
A list of the outstanding work and defects yet to be completed at the date of practical completion.
Practices aimed at ensuring the quality of materials and workmanship in a project.
A chart used to define roles and responsibilities in a project, indicating who is Responsible, Accountable, Consulted, and Informed.
The draft as built documents.
A formal request for suppliers to submit a proposal to provide goods or services.
A formal request for suppliers to submit a quotation to provide goods or services.
A formal request from a contractor to the client or engineer for clarification or additional information about project details.
A graphical representation of cumulative project data, such as cost or progress, over time.
A document outlining the amount allocated to each work item in a project.
The gradual expansion of project scope beyond its original objectives.
A detailed description of the work required for a project, including deliverables, timelines, and tasks.
Multiple occurrences of the same defect in the work with a common cause.
Detailed drawings prepared by contractors, suppliers, or fabricators showing how specific portions of the work will be fabricated or installed.
The process of verifying that all systems and components are functioning as intended.
The process of measuring materials and quantities from drawings to prepare a cost estimate.
A contract type where the contractor is paid for actual time spent and materials used.
The total cost associated with operating and maintaining a project or asset.
A project where the contractor delivers a fully operational facility to the owner, ready for immediate use.
A standard unit used to quantify materials or services.
A systematic method to improve the value of a project by analysing its functions and identifying cost-saving opportunities.
An addition, omission, substitution or change to the scope of or requirements for the project or work set out in an agreement
A formal document that modifies the original contract terms, scope, or price.
Information and documentation provided by suppliers regarding their products or services.
A hierarchical decomposition of the total scope of work to accomplish project objectives.
A group of related tasks within a project that can be assigned to a specific team or contractor.
A period during which the contractor is responsible for repairing or replacing defective work.
A project goal where all punch list items are resolved before project completion.
0423 825 235 hello@wambetilegal.com.au
Booking your 'test drive' or simply getting a quick answer to that nagging question is only a phone call away.