Due to the complex nature of Engineering, Procurement, and Construction (EPC) projects which involve:
managing time effectively is critical. When delays occur in EPC projects, they can disrupt the project's critical path, leading to cost overruns, reputational damage and, importantly, legal consequences.
This article explores the legal implications of delays and time overruns in EPC contracts and offers insights into how these issues can be managed and mitigated.
In EPC contracts, delays are broadly classified into three categories, each carrying distinct legal implications.
These are delays that arise due to unforeseen circumstances beyond the contractor’s control, such as natural disasters or force majeure events, strikes or political instability. In these cases, contractors may be entitled to extensions of time (EOT) without penalties.
These occur when delays are caused by the client or principal in the project or factors attributable to them, such as late approvals, site access issues, or changes to the project scope. Contractors are typically entitled to both time extensions and compensation for additional costs incurred due to these delays.
These are delays caused by the contractor's own fault or negligence. Such delays can lead to penalties, damages, or even termination of the contract. Contractors are not entitled to EOTs or compensation and may face legal liability for the principal’s losses.
Understanding the type of delay is essential, as it determines the contractor’s entitlement to time extensions, compensation, or liability for damages. Most EPC contracts include provisions to address these delays, but disputes often arise over their classification and the remedies available.
A common contractual tool to mitigate the risks of delays in EPC projects is the “delay liquidated damages” clause. Delay liquidated damages refer to a pre-agreed sum that the contractor must pay for each day or week the project is delayed beyond the agreed completion date. These clauses are designed to compensate the principal for losses caused by the delay, such as lost revenue or additional project financing costs.
From a legal perspective, the enforceability of liquidated damages clauses depends on several factors, which include:
Delay liquidated damages clauses provide a measure of certainty for both parties in the EPC contract by setting clear financial consequences for delays. However, their enforcement can lead to contentious disputes if the contractor believes the delay was excusable or partially caused by the principal.
In many EPC contracts, provisions for EOTs are included to allow the contractor additional time to complete the project without incurring delay liquidated damages.
These provisions typically apply in cases of excusable or compensable delays. Contractors seeking EOT must follow strict procedures set out in the contract, including:
Failure to comply with these requirements can result in the contractor’s EOT claim being rejected, making them liable for liquidated damages or other penalties. From a legal standpoint, delay claims are often a source of conflict in EPC contracts.
Disagreements typically arise over:
To avoid such disputes, both parties should clearly define the circumstances under which EOT is granted and ensure that procedures for making delay claims are reasonable and well-documented.
The doctrine of force majeure plays a vital role in EPC contracts when unforeseen events make project completion impossible or significantly delay progress.
Force majeure clauses typically excuse both parties from performing their non-financial obligations for the duration of the event. Events often considered force majeure typically include:
For a force majeure claim to be valid within an EPC contract, the event must typically meet the following legal criteria:
Force majeure clauses can lead to time extensions but do not usually provide compensation for additional costs incurred unless explicitly stated in the construction contract. The legal challenge with force majeure often lies in proving that the event qualifies under the contract’s definition and that it genuinely prevented the performance of non-financial obligations.
Delays can also result in contractor liability and, in severe cases, lead to termination of the contract. In such severe scenarios, if the contractor is responsible for substantial non-excusable delays, the principal may elect to invoke termination clauses to exit the construction contract and seek damages.
Termination for delay can have serious legal and financial consequences for the contractor, including:
However, termination for delay is often a last resort and must follow the specific procedures outlined in the construction contract, including proper notice to the contractor and an opportunity for remediation.
From a legal perspective, wrongful termination due to delays can expose the principal to significant liabilities, including compensation for lost profits and reputational damage. Both parties must ensure that the contract’s termination provisions are clear and adhered to strictly to avoid unnecessary litigation.
Delays in EPC projects frequently lead to disputes, especially when significant sums are at stake due to liquidated damages or compensation claims. To manage these disputes, most EPC contracts include provisions for dispute resolution mechanisms such as:
A well-drafted dispute resolution clause in an EPC contract can help avoid protracted legal battles and reduce the overall cost and time spent on resolving delay-related conflicts.
It is critical to involve legal counsel early in the tender process of your EPC or construction contract and throughout the project.
Wambeti Legal can assist you with key legal concerns around delays and time overruns by:
This article is of a general nature and should not be relied upon as legal advice. If you require further information, advice or assistance for your specific circumstances, please contact Wambeti Legal.